Before a grant end date, buy only what can be received, and in most cases distributed or put to use, inside the implementation period. A signed purchase order is usually not enough. Work back from the end date through distribution, inland transport, clearance and supply, check your donor’s own eligibility rules, and keep dated proof of every handover.
Our South Sudan humanitarian supply calendar covers what year-end money should buy and when it should move by road. This post takes the next question: once you have chosen the items, what will your donor accept as delivered, and what can still realistically arrive in time?
Why is the grant end date not your order deadline?
Because most donors judge the cost by when the goods were used for the project, not when you committed to buy them. DG ECHO says it plainly: a cost is incurred when the goods have been used in connection with the Action, and issuing a purchase order “is not sufficient for the costs to be eligible” (DG ECHO Partners’ Helpdesk, eligibility conditions). For supplies, ECHO links eligibility to supplies distributed or made available to beneficiaries during the implementation period.
The real deadline is the end date minus distribution or installation time, and every step before it.
What counts as delivered under each donor’s rules?
The rules differ by donor, and your signed agreement overrides any summary, including this one. The table sets out what each donor’s own published documents say.
| Donor | What the published rules say about goods | After the end date |
|---|---|---|
| DG ECHO (EU) | Supply costs relate to supplies distributed or made available to beneficiaries during the implementation period. Goods bought near the end and not distributed by the end are in most cases declared ineligible unless duly justified. | Late invoices are eligible only if the debt existed during the Action. Remaining goods: no-cost extension first, then transfer. |
| OCHA country-based pooled funds | Eligible costs include goods delivered to affected people as targeted in the proposal, with transport, storage and distribution. Costs outside the approved period are ineligible. | Payments within a 60-day liquidation period are eligible if linked to activities in the project period. New commitments after the end date are ineligible. |
| FCDO (UK) | The Project End Date is the latest point at which the partner may incur costs paid from the grant. | Outstanding claims are due no later than six months after the Project End Date. |
| US federal awards under 2 CFR 200 | Costs other than closeout costs must be incurred during the approved budget period. | Obligations must be liquidated, and final reports submitted, within 120 days of the end of the period of performance. |
Sources: DG ECHO, remaining goods; OCHA CBPF Global Guidelines, December 2022, paragraphs 305 and 307; FCDO Accountable Grant Arrangement template v3.5; 2 CFR 200.403(h) and 2 CFR 200.344.
Two cautions. The liquidation and claims windows are for paying for things that happened inside the period; they are not extra time to receive goods. And teams holding US-funded awards, including those that came through former USAID humanitarian funding, should read the standard provisions in their own award rather than assume which rules apply.
How do you work back from the end date?
- Find the test that applies. Read the eligibility clause in your own agreement: received, distributed, installed or simply incurred. Ask your grants team in writing if it is unclear.
- Set the last distribution or installation date. Allow for staff, transport to sites and any community process.
- Subtract inland transport. Use the season you will actually be moving in. Our road vs air comparison explains why a rushed move often ends up on an aircraft.
- Subtract receipt and inspection. Goods should be counted, checked against the order and signed for at your warehouse before they move on.
- Subtract supply time as the supplier states it. Ask each supplier for a written delivery date, and whether the items are held in country or must be imported and cleared.
- Subtract your own approvals. Tender or quotation rules, committee sign-off and any donor prior approval all take time before a purchase order can go out.
- Compare the result with today. If the order date has passed, cut the quantity, change the item, or raise an extension now rather than in the last month.
How realistic is the lead time you have been given?
Test it. The biggest single question is whether the goods are already in the region. Items held in stock locally avoid manufacturing, sea freight and import clearance; items that must be imported carry all three. Our guide to what you can buy in country and what you must import sets out which categories usually fall where.
Ask the supplier to confirm in writing where the stock sits today, the delivery terms and place, and what happens if the date slips. SLS holds stock in Juba and Nairobi, and quotes state the delivery terms; no supplier, SLS included, should be giving you a delivery promise it cannot document. The same pressure tests from our supplier pre-qualification checklist apply: in-country presence and a traceable delivery record matter more than a confident date.
Late-year buying also tempts teams to switch to air freight to make the date. Price that properly with a total landed cost comparison before you commit: a cheaper unit price flown in at speed is rarely the cheaper order.
Can a partial delivery still count?
Often yes, if you plan for it. Split the order into lots that can each be received, signed for and distributed on their own, and ask the supplier to invoice each lot separately. What arrives and is used inside the period can then be charged.
What does not work is a single invoice for the whole order with half the goods still in transit at the end date. Under ECHO’s rules, goods bought near the end and not distributed by the end are in most cases ineligible unless justified (DG ECHO, remaining goods). ECHO also warns that equipment bought towards the end of an Action is in most cases treated as not necessary unless operationally justified.
Which documents do donors and auditors look for?
Every pooled fund cost must be “backed by original supporting evidence” in line with the approved proposal and period (OCHA CBPF Global Guidelines, paragraph 304), and FCDO requires records of all procurement activity to be kept and shown on request. A file that will stand up at audit usually holds:
- the quotations or tender record that justify the choice of supplier and show value for money;
- the purchase order, dated inside the period and matching the approved budget line;
- the supplier’s delivery note or waybill, and your goods received note, signed and dated at receipt;
- the supplier invoice and proof of payment;
- stock issue records and distribution lists or installation handover reports, dated before the end date;
- an asset register entry for equipment, since FCDO, for example, treats items with a useful life over one year and a value above £500 as project assets.
What if the goods will not arrive in time?
Raise it early. Both ECHO and the OCHA pooled funds allow no-cost extensions through a formal amendment, decided case by case (CBPF Global Guidelines, paragraphs 170 to 172). Where goods remain after the results are met, ECHO sets an order of options: extension, then transfer to another ECHO-funded Action, then transfer to eligible recipients. None is guaranteed, so ask as soon as the delay shows.
If the goods are still needed and the grant cannot stretch, re-plan the purchase under the next allocation and use the dry season to move it, as the supply calendar describes.
Frequently asked questions
Is a purchase order signed before the end date enough?
Usually not. DG ECHO states that a legal commitment such as a purchase order is not sufficient for a cost to be eligible; the goods must be used for the Action. OCHA pooled funds rule out costs incurred outside the approved period. Check the eligibility clause in your own agreement, because the test differs by donor.
Can I pay the supplier after the grant ends?
Often yes, within limits. OCHA pooled funds accept payments in a 60-day liquidation period if linked to activities in the project period, FCDO accepts claims up to six months after the Project End Date, and US federal awards allow 120 days to liquidate obligations. These windows cover payment, not late delivery.
What happens to goods left over at the end?
It depends on the donor. ECHO asks partners holding remaining goods to request a no-cost extension first, then to transfer the goods to another ECHO-funded Action, then to eligible recipients. FCDO keeps ownership of project assets until it approves transfer or disposal. Agree the plan with your donor before the end date, not after.
Should I buy equipment in the last month of a grant?
Only with a clear operational reason you can write down. ECHO says equipment bought towards the end of an Action is in most cases treated as not necessary and declared ineligible unless duly justified. If the pump or tank is needed for the next phase, it may belong in the next budget instead.
If you are working back from a grant end date and need a quotation that states stock location and delivery terms, email sales@maji-safi.org, WhatsApp +254 722 824 480, or request a quote.